Progress West Health Care Center
Owner/Developer: BJC
Architect: HOK
Engineer: KJWN
Duration of Project: 18 months
Completion Date: December 2006
Building Scope:
Complete plumbing system of hospital.
Services Provided:
Design assist and installation.
Challenges:
Coordination do to limited space above ceilings and time durations to install due to the
aggressive schedule.
Comments:
General Contractor and MEPF worked together very well. A great team effort and approach to
getting the job coordinated and installed. A lot of up front time spent on establishing
elevations and location of systems.